Commercial Asphalt Milling & Resurfacing in Northern Virginia, Maryland & Washington, DC

Commercial asphalt milling and resurfacing removes deteriorated pavement at a specified depth and replaces it with new asphalt. When the remaining pavement structure is suitable, this approach can renew a worn parking lot or access road while retaining sound pavement underneath.

Espina Paving, Inc. provides commercial milling and resurfacing throughout Northern Virginia, Maryland and Washington, DC. We work with property owners, property and facility managers, associations and institutions to plan improvements around pavement conditions, vehicle use and operating schedules.

Our resurfacing capabilities include:

  • Asphalt milling and removal of deteriorated surface pavement.
  • New asphalt surface installation and compaction.
  • Localized full-depth repairs where underlying pavement has failed.
  • Coordination with drainage structures, curbs and adjoining concrete.
  • Phased construction and pavement markings for commercial properties.

For a broader overview of pavement construction and rehabilitation options, explore our commercial asphalt paving services.

What Is Asphalt Milling and Resurfacing?

Asphalt milling, also called cold planing, uses a milling machine to remove a controlled thickness of existing pavement. Resurfacing installs a new asphalt layer over the prepared surface.

Together, these operations are often called a mill and overlay. Removing existing material before paving helps manage finished elevations where asphalt meets curbs, gutters, entrances, sidewalks and drainage structures.

An overlay can also be installed without milling where pavement conditions, available elevations and project specifications allow. The appropriate method depends on what the existing pavement can support and how the finished surface needs to function.

Project Example: Night Milling and Resurfacing at Reagan National Airport

Espina Paving performed nighttime milling and resurfacing of a parking lot serving office buildings at Ronald Reagan Washington National Airport in Arlington, Virginia. The work was scheduled at night because of the airport’s heavy daytime vehicle traffic.

The documented project included:

Project component
Work performed
Milling
A Wirtgen 1200 milling machine removed the top two inches of deteriorated asphalt.
Resurfacing
The crew placed a new two-inch layer of 9.5 mm asphalt surface course.
Compaction
An Ingersoll Rand roller compacted the new pavement.

These project details are confirmed in Espina Paving’s published project description. Asphalt Contractor Northern Virginia

This project illustrates how pavement rehabilitation can be planned around a busy property’s operating demands. Its milling depth and asphalt mixture were specific to that job; other properties require their own evaluation and specifications.

See the Reagan National Airport mill-and-overlay project on our paving project videos page.

Is Your Commercial Pavement a Candidate for Resurfacing?

Milling and resurfacing may be appropriate when deterioration is concentrated in the upper pavement and the remaining structure can support the intended traffic. Localized failures may need deeper repairs before the broader area is resurfaced.

Conditions worth evaluating include:

  • A rough, weathered surface or loss of aggregate.
  • Surface irregularities and deteriorated previous repairs.
  • Worn pavement around entrances, drive aisles and parking spaces.
  • Existing overlays that have raised the surface near curbs or drains.
  • Recurring potholes, settlement, rutting or extensive cracking.

These symptoms do not all call for the same treatment. Widespread alligator cracking, deep movement or recurring failures can indicate structural or drainage problems that a surface overlay alone will not resolve. Asphalt Paving Handbook

Pavement condition
Approach to consider
Suitable existing pavement with room for an additional layer
Overlay with appropriate preparation and transition work.
Deteriorated upper asphalt with sound pavement below
Controlled-depth milling and resurfacing.
Generally suitable pavement with isolated failed areas
Localized full-depth repairs combined with resurfacing.
Widespread base or subgrade failure
More extensive investigation and reconstruction.

Properties We Serve

Espina Paving’s commercial resurfacing services support:

  • Office buildings, business parks and retail properties.
  • Apartment communities, condominiums, townhouses and HOAs.
  • Industrial facilities, warehouses and service areas.
  • Schools, healthcare facilities and institutional campuses.
  • Municipal properties and government facilities.

For projects involving the entire parking facility, review our commercial parking lot paving services for related construction, repair and parking-area improvements.

How a Commercial Milling and Resurfacing Project Is Planned

1. Evaluate the Existing Pavement

The evaluation considers visible distress, previous repairs, drainage, traffic loads and adjoining surfaces. Where conditions are uncertain, cores, testing or engineering review may be needed to establish a suitable repair strategy.

2. Define the Scope and Construction Phases

The scope should identify milling limits, removal depth, repair areas, asphalt requirements and transitions. Planning also addresses parking restrictions, tenant notices, deliveries, pedestrian access and the sequence for closing and reopening work areas.

3. Mill and Inspect the Exposed Surface

The milling machine removes pavement to the specified depth. The exposed surface is then checked for conditions that need additional attention before paving, including weak areas that were less apparent during the initial inspection.

4. Complete Repairs and Prepare for Bonding

Required deeper repairs and associated corrections are completed before resurfacing. The receiving surface is cleaned, and a suitable tack coat is applied to help bond the new asphalt to the pavement below. Asphalt Paving Handbook

5. Place and Compact the New Asphalt

New asphalt is placed at the specified thickness and compacted. Placement must account for joints, edges and connections to existing pavement, concrete aprons, gutters and drainage structures.

6. Finish Markings and Coordinate Reopening

Where included, parking lot striping and pavement markings are coordinated with the approved layout. Reopening is based on pavement cooling, site conditions, anticipated vehicle use and completion of the necessary safety measures.

Drainage, Pavement Elevations and Accessibility

Resurfacing should be planned around how water leaves the property and how people move through it.

Milling can provide room for new asphalt at existing elevations, but it does not automatically correct ponding. Low spots, settled pavement, inadequate grades or drainage-structure problems may require additional work.

Before construction, review:

  • Connections to storm drains, gutters and adjoining pavement.
  • Finished heights beside curbs, entrances and concrete aprons.
  • Accessible parking spaces, access aisles and pedestrian routes.
  • Curb ramps, sidewalk connections and changes in level.

Parking-lot resurfacing is generally an alteration under the ADA Standards, and applicable accessible-parking requirements must be addressed. The required scope depends on the facility and the work being performed; repainting an existing layout alone does not establish compliance. access-board.gov

Where the project calls for adjoining improvements, Espina Paving can coordinate commercial concrete work with asphalt resurfacing. Accessibility details should be reviewed against applicable requirements with the appropriate design professional or authority when needed.

Phased and Nighttime Paving for Occupied Properties

Occupied properties need a practical access plan as well as a paving plan. Construction may be divided into sections or scheduled during lower-traffic periods where site conditions allow.

Planning should establish:

  • Which parking areas and entrances close during each phase.
  • How employees, residents, customers and deliveries reach the property.
  • How accessible pedestrian routes and emergency access are maintained.
  • Where equipment and trucks operate without conflicting with public circulation.
  • How schedule changes and reopening instructions are communicated.

Night work depends on lighting, weather, asphalt supply, local restrictions and project logistics. Some areas will still require temporary closure; the feasible schedule should be established before work begins.

What Affects Commercial Asphalt Resurfacing Cost?

The cost depends on the work required beneath and around the new surface, as well as the area being paved. Important factors include:

  • Milling depth and asphalt thickness.
  • The quantity of full-depth repairs or base correction.
  • Asphalt mix requirements and anticipated vehicle loads.
  • Drainage, utility and concrete adjustments.
  • Truck access, hauling and material handling.
  • Construction phases, night work and traffic control.
  • Pavement markings and accessibility-related improvements.

For budgeting, request a proposal that separates the main resurfacing work from identified repairs, allowances and optional improvements. Agree on how concealed deterioration will be documented and priced if it is uncovered during milling.

Milling and Resurfacing Across the Washington Metropolitan Area

Based in Woodbridge, Virginia, Espina Paving serves commercial properties throughout Northern Virginia, Washington, DC and the Maryland portion of the Washington metropolitan area.

Whether you manage one parking lot or a property with multiple paving phases, the starting point is a clear assessment of the pavement, its use and the improvements needed.

Frequently Asked Questions

What is the difference between asphalt milling and resurfacing?

Milling removes existing asphalt to a specified depth. Resurfacing installs a new asphalt layer over a prepared pavement surface. A mill-and-overlay project combines both operations to renew the surface while managing pavement elevations.

Does every parking lot need milling before an overlay?

No. An overlay without milling may be suitable where the existing pavement, drainage and available elevations allow. Milling is useful when deteriorated material needs removal or when adding asphalt would create problems at curbs, entrances, drains or adjoining surfaces.

Is a two-inch asphalt replacement enough for every commercial property?

No. Two inches was the documented removal and replacement depth for Espina Paving’s Reagan National Airport project. Other properties may need different depths, mixtures or structural repairs based on pavement condition, traffic loads and project specifications.

Can a commercial property remain open during resurfacing?

In some cases, construction can be phased to retain limited access to other parts of the property. The work area requires closure, and the plan must address pedestrians, accessible routes, emergency access and vehicle circulation. Feasibility depends on the site layout and scope.

How much does commercial asphalt milling and resurfacing cost?

A useful estimate requires an evaluation of the pavement and proposed scope. Area, milling depth, asphalt thickness, underlying repairs, drainage work, site access, phasing and markings all affect cost. Comparing clearly defined scopes is more useful than comparing price per square foot alone.

When can vehicles return to resurfaced asphalt?

Reopening depends on asphalt cooling, weather, layer thickness, anticipated loads and site conditions. The contractor should provide instructions for the completed work. Heavy trucks, tight turning movements and prolonged stationary loads may require additional precautions.

Does parking lot resurfacing require an ADA review?

Parking-lot resurfacing is generally an alteration under the ADA Standards, so applicable accessible-parking requirements must be addressed. Review the spaces, access aisles, slopes, signage and connecting routes as applicable to the project. Existing striping alone does not establish compliance.

How long will resurfaced commercial asphalt last?

There is no single service life for every resurfacing project. Performance depends on the remaining pavement structure, preparation, drainage, asphalt materials, compaction, traffic, weather and maintenance. Addressing underlying failures and maintaining the completed pavement supports long-term performance.

Request a Commercial Pavement Evaluation

If your parking lot or access road is worn, uneven or repeatedly repaired, Espina Paving can help determine whether milling and resurfacing is appropriate and identify related work to include in the scope.

Call (703) 491-9100 or request a commercial milling and resurfacing evaluation to discuss your property, scheduling needs and project goals.